Dispute Management

Location:  PMKI > IT & Construction Industries > Dispute Management. 

The PMKI Library

PMKI Index
Download
the PMKI
Taxonomy
Disputes in the construction and engineering industries are common and often involve large amount so money. This page looks at contract dispute management from the perspective that preventing disputes is better than resolving disputes. But when a dispute arises you need to know how to respond effectively.

Topics included in Dispute Management in construction and engineering:

- Dealing with poor performance
- Contract & Commercial Management
- Dispute Management
   - General Concepts for Minimizing Disputes
   - Managing Contract Disputes
   - Defective Work Claims
   - Delay and Disruption Claims
   - Legal Dispute Resolution Processes  
- Useful External Web-links & Resources.

Other related sections of the PMKI:

- Claims and Forensic Analysis
- ADR and Dispute Management Services
- Basic Contract Law & Procurement 
- Inter-personal Conflict Management


Dealing with poor performance

ConfusionAt all stages, of dispute management, procedural fairness is vital.
 
Art: Fairs Fair - Process & Procedural Fairness. When you have to deliver bad news to a person, the processes you use are at least as important as the decision you have made.

Managing a contractor (or subcontractor) that is failing to perform raises some interesting legal and contractual challenges. My suggestions are:

What not to do: Do not get directly involved in 'helping' the contractor plan or manage its work, if you do you will accept some responsibility for future performance. But do be responsive to sensible suggestions to overcome issues.

What to do:

  1. Make sure payments accurately reflect work actually accomplished.
  2. As far as possible make sure all of the client inputs are delivered in accord with the original program requirements. If these are delivered later than this the contractor may be able to claim it was 'pacing' its work to accommodate the delay and if the deliveries actually cause a delay the contractor can claim the delivery was the overriding cause of the delay and seek EOTs with costs - see concurrent and parallel delays on our claims and forensic analysis page.
  3. Be proactive in supporting problem solving processes. This may include involving other subcontractors and suppliers and investing your time and effort.
  4. Keep really accurate records of everything done on a daily basis. Date stamped photographs help. Signed records are good. Make sure the progress information is shared with the contractor (no surprises).
  5. Expect lots of claims from the contractor and gear up early.
  6. Don't assume the contractors Head Office knows what is going on. Regular requests to the head office to explain schedule slippages each month (eg, contract issued last month was for 1000cu.m. only achieved was 700cu.m - please explain) will put pressure on the site to perform. Focus these requests on one or two key metrics only.
  7. It may help to get expert advice early (but this tends to be expensive).


Easy CPM One of the best tools for avoiding poor performance and managing issues proactively to avoid claims is a competently developed and maintained critical path (CPM) schedule. Easy CPM is a course-in-a-book that provides practical training and guidance to individuals and organizations involved in developing or using CPM schedules based on the Critical Path Method (CPM). It is designed to act as both a reference, and practice guide, for people implementing CPM scheduling after they have learned to use the CPM scheduling software of their choice.

Top 


Contract & Commercial Management

Contract ManagementPreventing disputes is better than resolving disputes. The introduction of Adjudication in the UK and Australia has pressurized project administration, causing a radical re-think of many traditional project management and contract management processes. The Acts apply to every business involved in Building and Construction including contractors, subcontractors, clients, suppliers and professional firms. Construction industry professionals need to address and manage the impact of the Acts on projects in which they are involved - See Adjudication below.

Effective contract management requires:

  • Leadership – Executive support to encourage good performance from subcontractors and suppliers  [see: Leadership & Motivation]
  • Strategy – Policy formation for robust, systematized mapping of strategic and operational goals and aligning these with contract requirements
    [see: Aligning Projects, Programs and Strategy]
  • Stakeholder engagement – Plan and track business relationships with all suppliers and subcontractors  [see: Advanced Stakeholder Engagement]
  • Risk Management – Implementation of effective risk management that includes supplier and subcontractor risks   [see: Advanced Risk Management]
  • Solution Requirements Management – Design and segmentation of product/service categories for management effectiveness
  • People Development – Closing skills gaps and development of team members as trusted advisors managing suppliers and subcontractors is a specific skill set
  • Financial – Link contract terms and conditions to price and cost analysis, pay for performance
  • Execution & Delivery – Strong focused on results, performance based contracting, regular reviews of the procurement systems
  • Information Systems / Knowledge Management – Procurement support using automation to systematically capture and manage contract and relationship performance

Top


Dispute Management

Contract DisputesGeneral Concepts for Minimizing Disputes

WP: Issues Management. Before declaring something a dispute, consider managing it as an ‘issue’, at least to begin with. Defining a problem an ‘issue’ rather than a ‘dispute’ means you can apply normal project management techniques to manage the problem.

WP: Negotiation & Mediation. Increases the formality and introduces ‘sides’ into the process. The negotiation process remains totally within the control of the parties and may be assisted by a trained mediator.

WP: Win-Win Negotiations. A win-win approach to negotiation can deliver higher value at lower risk than a win-lose scenario.


Managing Contract Disputes

Click through to our procurement management page for more on:
- Basic contract law
- Common forms of contract
- The Law of Contract

WP: Dispute Management in Contracts. An overview of the escalating options for managing disputes from problem solving and negotiation through to litigation and consequences of the choices made to resolve the dispute.

Blg: Using a Risk Management approach for Assessing Claims. Balancing the inevitable costs of pursuing a claim against the possible gains is a difficult but necessary decision before moving forward.

WP: Contract Termination. When all else fails contract termination may be the only option; but beware - terminating a contract is a high risk activity. This White Paper takes a layman's look at the risks and issues. 

CRC For Construction Innovation - The CRC-CI website closed 30th March 2010, Documents from the CRC-I project, a Guide to Leading Practice for Dispute Avoidance and Resolution are available for download:
- Guide to Leading Practice for Dispute Avoidance and Resolution
- Guide to Leading Practice for Dispute Avoidance and Resolution: An overview
- Dispute Avoidance and Resolution (literature review)
- Causal Ascription of Disputes (report)
- Strategies for Dispute Avoidance (report)
- An exploratory study of project dispute pathogens (journal article)
- Causal Modelling of Construction Disputes (refereed conference paper)


Defective Work Claims

A defective work claims is the most common claim made by building owners against their building or construction contractor. The cost and consequences associated with resolving a defective work claim can be minimized if the contract is prepared for each individual project setting out effective and feasible methods of risk allocation together with clear obligations in relation to standards, quality and the reliance placed on the contractor's skill and expertise. 

PP: Defective Work Claims. This paper canvases both contractual and common law aspects of making and defending claims for defective work in Australia.
Prs: Defective Work Claims. Download the shorter PowerPoint presentation

 

Delay and Disruption Claims

The techniques needed for making and defending delay and disruption claims are 
Mosaic's Claims and Forensic Analysis page
- Forensic analysis and reporting
  -  Assessing Delay and Disruption
  -  Concurrent and Parallel Delays
  -  Referenced Court Judgements 
- Claims & Expert Witness


Dispute Resolution

Legal Dispute Resolution Processes

Preventing disputes is better than resolving disputes. Discussion, problem solving, or mediation offer better options for dispute resolution, but need both parties to cooperate. The legal options below offer finality and enforcement, but you may not liek the answer the person making the decision comes to.

WP: Dispute Management in Contracts. An overview of the escalating options for managing disputes from problem solving and negotiation through mediation, expert determination and arbitration, to litigation and consequences of the choices made to resolve the dispute.

Art: Delivering Expert Evidence is Becoming Harder. This article discusses a number of recent judgements that seem to have re-framed expert evidence, 'the court is not compelled to choose only between the rival approaches and analyses of the experts. Ultimately it must be for the court to decide as a matter of fact what [occurred]. '...there is an overriding objective of ensuring that the conclusions derived from that analysis are sound from a common-sense perspective'. 


Adjudication

The introduction of Adjudication in the UK and Australia has pressurized project administration, causing a radical re-think of many traditional project management and contract management processes. The Acts apply to every business involved in Building and Construction including contractors, subcontractors, clients, suppliers and professional firms. Construction industry professionals need to address and manage the impact of the Acts on projects in which they are involved. For examples, see the Casewatch series on Adjudication.


Arbitration

Arbitration is used to solve issues involving more complex evidence. Typically, there is evidence provided by both parties, the parties respond to the other side’s submissions and then the Arbitrator issues a determination. Arbitration determinations are enforceable through the courts. Unlike sovereign law which can usually only be enforced in the country where the court is constituted, international arbitration awards can be enforced in most countries. Arbitrators are bound by the concept of ‘natural justice’ and are subject to a limited oversight by the court systems to ensure due process, but once an Arbitrator is appointed by the parties, the Arbitrator will determine the solution and the outcome of the dispute.  For examples, see the Casewatch series on Arbitration.


Litigation

Involves formal processes conducted in a court of law with the full power of the state available to enforce conformance with the trial process and the determination of the court. The resort to law should be seen as the final option when all else has failed. Unlike all of the preceding options, court proceedings are public and open to scrutiny.

Top


Useful External Web-links & Resources

Construction and Engineering Disputes

Doyles Construction Lawyers - Australia’s largest specialist construction law firm: https://doylesconstructionlawyers.com/ 

Resolution Institute (formally IAMA and LEADR) - Australia's largest, independent and most experienced arbitration and mediation service: https://www.resolution.institute/

The Society of Construction Law (UK). The society works to promote education, study and research in the field of construction law and related subjects (including adr, arbitration and adjudication), both in the UK and overseas: https://www.scl.org.uk/

Society of Construction Law Australia. A single national organization of members, at all stages of their professional career, who share an interest in construction law: https://www.scl.org.au/


Construction and Engineering Good Practice

The Chartered Institute of Building (CIOB). the world's largest and most influential professional body for construction management and leadership: https://www.ciob.org/about

Constructing Excellence - CE (UK) aims to achieve a step change in construction productivity by tackling the market failures and promoting continuous improvement: http://www.constructingexcellence.org.uk

World Commerce & Contracting - The International Association for Contract & Commercial Management world-class standards in contracting and relationship management process and skills: https://www.worldcc.com/

ICPMA - The International Construction Project Management Association (ICPMA) is an international umbrella association focusing on international Knowledge Management, the General Annual Meeting, working groups and publications: http://www.icpma.net

Major Projects Association (UK). Brings together learning, innovation and good practice from many different sources such as learning legacies by major projects, other related knowledge hubs and websites: https://majorprojects.org/

Top

Stakeholder Work Sheet

Stakeholder on a Page


Work Performance Management

Risk Register


Risk Management Plan

Project Charter Template
Stakeholder Work Sheet

Stakeholder on a Page


Work Performance Management

Risk Register


Risk Management Plan

Project Charter Template